DCM Outdoor · Charleston, SC
Selective demolition at the pool side, disposal, and full replacement of decking, stairs, and guardrails on the remaining structure — built on existing framing where sound.
01
Site conditions
Multi-level pressure-treated wood deck with landings, multiple stair runs, and guardrails with square balusters. Field documentation (July 2026) includes on-site measurement and a three-person walkthrough.
Finish failure Solid reddish-brown coating is peeling across decking, rails, and posts; exposed wood is greyed with dark moisture staining on many boards.
Safety Failed stair guard (split/rot at handrail), tread edge damage, and auxiliary metal handrail on one stair run to be removed with rail rebuild.
Pool area Lower pool-adjacent platform remains in scope for selective removal and disposal (see prior site photos in appendix).
02
Scope of work
03
Material plan
Pricing per Lowe's list (29403). Estimated 9% SC sales tax on materials.
| Material | Qty | Unit | Extended |
|---|---|---|---|
| 5/4×6×10 PT deck boards | 58 | $9.28 | $538.24 |
| 2×4×12 PT lumber | 9 | $10.38 | $93.42 |
| 2×12×12 ground-contact PT lumber | 5 | $37.08 | $185.40 |
| 2×6×12 PT lumber | 5 | $14.58 | $72.90 |
| 4×4×8 ground-contact PT posts | 8 | $10.48 | $83.84 |
| 2×2×36 PT balusters | 75 | $1.78 | $133.50 |
| Lumber subtotal | $1,107.30 | ||
| Estimated 9% tax | $99.66 | ||
| Lumber total | $1,206.96 | ||
| Item | Qty / note | Budget |
|---|---|---|
| 3″ ACQ-rated deck screws, 5-lb boxes (Deck Plus ~$29.98/box) | 3 | $89.94 |
| Exterior structural screws | 2 boxes | $94.00 |
| Butyl joist tape | 250 LF | $100.00 |
| ½″ galvanized bolts, washers & nuts | 20 sets | $60.00 |
| Post tension ties / connectors | 8 | $120.00 |
| Exterior rail brackets / connectors | Allowance | $60.00 |
| End-cut wood preservative | 1 gallon | $35.00 |
| Exterior construction adhesive | 6 tubes | $44.88 |
| Demolition saw-blade packs (DeWalt 16-pc ~$19.98) | 2 | $39.96 |
| Hardware subtotal | $643.78 | |
| Estimated 9% tax | $57.94 | |
| Hardware total | $701.72 | |
| Working material total | Total |
|---|---|
| Lumber and balusters (incl. tax) | $1,206.96 |
| Hardware and supplies (incl. tax) | $701.72 |
| Current material budget (calculated) | $1,908.68 |
| Purchasing budget carried on job — rejected boards, missing connectors, incidentals | $2,150.00 |
| Allowance item | Included | Each additional |
|---|---|---|
| Joist replacement | Up to 2 | $____ / joist |
| 6×6 post replacement | 0 | $____ / post |
| Extra dumpster pull | 0 | Cost + $____ |
04
Investment
Fixed-price proposal for labor, disposal, and delivery per scope above. Material purchasing budget: $2,150.00 (Lowe's lumber/hardware per page 3 — calculated $1,908.68 + buffer for rejected boards and incidentals). Dumpster, delivery, stain, and hidden framing repairs are separate lines below.
| Line | Description | Amount (USD) |
|---|---|---|
| 1 | Selective demolition — pool-side removal; remove all existing decking, stairs, and guardrails on remaining structure; load-out | $________ |
| 2 | Disposal — 15 yd roll-off (delivery, pickup, dump fees) | $________ |
| 3 | New deck surfacing — PT decking on existing framing (~260 SF field) | $________ |
| 4 | New stair construction — stringers, treads, fasteners (approx. three runs) | $________ |
| 5 | New guardrail system — posts, rails, balusters, caps (~140–170 LF) | $________ |
| 6 | Materials — lumber, balusters, fasteners & supplies (Lowe's purchasing budget; see page 3). Calculated $1,908.68; $2,150.00 carried on job. | $2,150.00 |
| Total investment (PT, natural — no finish coat) | $________ | |
| Option | Description | Amount (USD) |
|---|---|---|
| A | Clean, prep, and apply two coats exterior solid/semi-solid stain (color TBD after sample) | $________ |
[e.g. 1-year workmanship on carpentry installation; manufacturer terms on materials.]
05
Terms & acceptance
Client authorization
I accept the scope, investment, and terms of this proposal.
DCM Outdoor
[Authorized representative]